March 2017 - August 2018 - £2.2M
Professional Team - Grosvenor/Sir Robert McAlpine/Arcadis/Cantillon
The project was located on London’s busy Oxford Street opposite the Selfridges department store, the Peabody Estate residents bounded the site to the other three elevations. One of the significant challenges on the project was that the upper four floors of the building were tenanted and had to remain live throughout demolition and structural alteration works detailed below.
Due to the close proximity of the tenants and neighbours, the noisy working hours were restricted to only 2 hours per day 8am -10am. The scope of our works to the upper floors included:-
The project was extremely complex due to the nature of the works and the restricted noisy working hours. All of our works had to be sequenced and co-ordinated with the steelwork contractor undertaking the strengthening works to ensure that the structural stability of the building was maintained with minimal need for temporary works.
Careful co-ordination with other contractors was essential as the site logistics were very restricted and there was only one loading bay with a single conveyor belt out of the basement and one from the first floor windows to remove all debris from site. Our works were carried working concurrently with several other contractors employed by the Main Contractor in order to complete the works in a tight programme.
Copyright © 2018 Salter Demolition - All Rights Reserved.
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.